Frequently Asked Questions

How long will it take to get sealed truss designs?

Depends of current backlog but typically it takes between 5 to 10 work days.

How long will it take to get trusses……what is your current lead time?

We normally require a two week lead time on all truss deliveries after sealed engineering is completed. This can change depending on backlog.

Will my truss price change if it takes a couple of months to get a permit?

Price quotes are firm for acceptance for 30 days, and will remain the same through delivery providing delivery is scheduled within 90 days after engineering.

What do I need to do to get truss pricing?

We will need a set a building plans complete with information regarding wind speed, exposure, any special loading requirement, and contact information for someone who can answer technical questions.